London Olympics exceed initial budget by £6.52bn

When is "under budget" not "under budget"?

By Alex Hern

BBC News, 1 February 2007:

How much will the Olympics really cost?

The overall budget for the London Olympics submitted in the bid to the International Olympic Committee was £2.4bn.

The figure came from a study carried out by construction company Arup in May 2002. It predicted the cost of the Games to be £1.8 billion.

The government then commissioned another report in 2004 carried out by accountants PriceWaterhouseCooper, who put the figure closer to £3.2bn. The government settled for a compromise figure of £2.4bn.

Sign up for The New Statesman’s newsletters Tick the boxes of the newsletters you would like to receive. Quick and essential guide to domestic and global politics from the New Statesman's politics team. The best of the New Statesman, delivered to your inbox every weekday morning. The New Statesman’s global affairs newsletter, every Monday and Friday. A handy, three-minute glance at the week ahead in companies, markets, regulation and investment, landing in your inbox every Monday morning. Our weekly culture newsletter – from books and art to pop culture and memes – sent every Friday. A weekly round-up of some of the best articles featured in the most recent issue of the New Statesman, sent each Saturday. A weekly dig into the New Statesman’s archive of over 100 years of stellar and influential journalism, sent each Wednesday. Sign up to receive information regarding NS events, subscription offers & product updates.
I consent to New Statesman Media Group collecting my details provided via this form in accordance with the Privacy Policy

BBC News, 23 October 2012:

London 2012: Olympics and Paralympics £377m under budget

The cost of the London Olympics and Paralympics will be £377m less than expected, according to the Government.

The combined budget for the two events was £9.29bn, but the projected cost is £8.92bn.

Savings came from a drop in security, transport and construction expenses.

In other words, “Our £6.89bn overspend was actually just a £6.52bn overspend when all things are taken into account! Huzzah!”

The latest BBC News story doesn’t even mention the original estimates at all, although an earlier news story – from July – at least featured Hugh Robinson evading the question: 

Addressing the original bid budget of £2.4bn, Sports Minister Hugh Robertson said there was a “recognition right from the word go that figure would have to change dramatically on the basis of delivering the Games”.

We have always been at war with Eastasia.