Crossrail delayed until 2022 – and will cost an extra £450m to complete

Transport for London has announced a break in construction, in part due to social distancing measures.

By Rohan Banerjee

Crossrail – the planned 73-mile high-speed railway lines connecting Reading and Heathrow to the west of London to Abbey Wood and Shenfield in the east – has been delayed again until at least 2022.

Transport for London (TfL) has announced a break in construction, in part due to social distancing measures against the coronavirus pandemic. The decision means that the Elizabeth Line’s central section – the 26-mile stretch of underground tunnels that link London’s Paddington to Canary Wharf and out to Abbey Wood – will now open more than three years late.

Crossrail’s board said it could need an extra £1.1bn on top of the £2.15bn package it had agreed with TfL in December 2018 – representing £450m more than the estimates it put forward in November 2019. This could put the total bill for the project at over £19bn.

The infrastructure scheme was supposed to cost £14.8bn, with the Elizabeth Line meant to have begun operating in central London from December 2018. But various factors, including electrical faults encountered with the railway’s signalling system and health and safety conditions for workers, have contributed to delays since construction first began in 2009.

[Read also: The long and winding road to HS3]

Select and enter your email address Quick and essential guide to domestic and global politics from the New Statesman's politics team. A weekly newsletter helping you fit together the pieces of the global economic slowdown. The New Statesman’s global affairs newsletter, every Monday and Friday. The best of the New Statesman, delivered to your inbox every weekday morning. The New Statesman’s weekly environment email on the politics, business and culture of the climate and nature crises - in your inbox every Thursday. Our weekly culture newsletter – from books and art to pop culture and memes – sent every Friday. A weekly round-up of some of the best articles featured in the most recent issue of the New Statesman, sent each Saturday. A newsletter showcasing the finest writing from the ideas section and the NS archive, covering political ideas, philosophy, criticism and intellectual history - sent every Wednesday. Sign up to receive information regarding NS events, subscription offers & product updates.
  • Administration / Office
  • Arts and Culture
  • Board Member
  • Business / Corporate Services
  • Client / Customer Services
  • Communications
  • Construction, Works, Engineering
  • Education, Curriculum and Teaching
  • Environment, Conservation and NRM
  • Facility / Grounds Management and Maintenance
  • Finance Management
  • Health - Medical and Nursing Management
  • HR, Training and Organisational Development
  • Information and Communications Technology
  • Information Services, Statistics, Records, Archives
  • Infrastructure Management - Transport, Utilities
  • Legal Officers and Practitioners
  • Librarians and Library Management
  • Management
  • Marketing
  • OH&S, Risk Management
  • Operations Management
  • Planning, Policy, Strategy
  • Printing, Design, Publishing, Web
  • Projects, Programs and Advisors
  • Property, Assets and Fleet Management
  • Public Relations and Media
  • Purchasing and Procurement
  • Quality Management
  • Science and Technical Research and Development
  • Security and Law Enforcement
  • Service Delivery
  • Sport and Recreation
  • Travel, Accommodation, Tourism
  • Wellbeing, Community / Social Services
I consent to New Statesman Media Group collecting my details provided via this form in accordance with the Privacy Policy

Mark Wild, the Crossrail chief executive, said: “Our focus remains on opening the Elizabeth line as soon as possible. Now more than ever Londoners are relying on the capacity and connectivity that the Elizabeth line will bring and we are doing everything possible to deliver the railway as safely and quickly as we can.”

Crossrail’s board admitted that there had been “lower than planned productivity” in the construction of the railway’s shafts and portals, and that it had overestimated how quickly new stations could be built in central London. Covid-19, it said, had made these scheduling pressures worse, with strict limits on the number of staff able to work on site now imposed. 